How is the construction of Sami Verde phased?

Sami Verde will be developed in multiple phases, ensuring quality, tranquillity and clarity throughout the entire process.

The development consists of at least three phases. In Phase 1, approximately 10 homes will be realised. Sales for this phase are expected to start in the second quarter of 2026. Construction will commence once approximately 75% of the homes have been sold. The construction period for Phase 1 is estimated at around 12 months, with planned delivery in 2027.

The exact scope and planning of the later phases will be determined at a later stage. This approach provides flexibility to align the project optimally with market conditions and buyer demand.

This phased approach ensures that:

  • the project remains small-scale and well-organised

  • construction is driven by actual demand

  • quality and the living environment are safeguarded throughout the entire process

Please note: the exact planning and phasing are indicative and may be adjusted depending on sales progress and market conditions.